Did you know, as an MCS certified Installer, we can help you with you BUS grant application?

The Old Bridge Hotel

Key Facts

Location: The Old Bridge Hotel

Main Contractor: Entire Group Ltd

Project Value: £60,000.00

Disciplines

Project Value: £60,000.00

Entire Group Ltd carried out a commercial boiler room refurbishment for a very busy hotel in Huntingdon. The works consisted of the removal and replacement of 4no commercial boilers, including all associated pipework, pump upgrades, BMS panel upgrade and full system flushing. We also installed new hot water cylinders throughout various locations in the hotel, as well as cleaning & disinfecting of cold water storage tanks. This obviously had to be carried out as quickly and efficiently as possible to limit the disruption the the hotel and its guests.